SI3 STATUS AT PURDUE Oct 15 1999
STATUS OF CLAMSHELL #1
STATUS OF CLAMSHELL #2
CLAMSHELL #2 IS ON HOLD PENDING REPLACEMENT PARTS SINCE 9/15/99
STATUS OF LAYER 3
STATUS OF L3 BY LADDER
STATUS OF LAYER 4
To complete L4 we need to build:
5 out of 8 wafer chains are ready
3 out of 8 wafer chains had 4th wafer removed all are fine, will re-build WCıs after WC building machine is put back under CMM
Recovery of HL554 (fried, at Cornell, status from Eckhart?)
Plan for of starters not yet at Purdue?
STATUS OF LAYER 4 BY LADDER